Wastewater treatment
Federal contribution
$2.2M
$2,212,535
Federal share44%
of $5.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201420152016
Built
Approved 2.4 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Saint-Barnabé-Sud
- Construction start
- Aug 19, 2014(actual)
- Construction end
- Apr 6, 2016(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2014
- Construction end3 months lateforecast Dec 31, 2015
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44402 in the federal list. How to read these figures.