Highway 35 - Phase II
Federal contribution
$44.0M
$44,000,000
Federal share31%
of $140.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 28, 2005
ApprovedApr 26, 2006
200520072009201120132015
Built
Approved 12 months after the announcement.
- Program
- Canada Strategic Infrastructure Fund
- Ultimate recipient
- Province of Quebec
- Construction start
- Jan 1, 2009(actual)
- Construction end
- Oct 8, 2014(actual)
Against the original forecast
- Construction end10.5 years earlyforecast Mar 31, 2025
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44817 in the federal list. How to read these figures.