Highway 1 - West of Swift Current
Federal contribution
$2.5M
$2,500,000
Federal share50%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 13, 2013
2014
Built
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Saskatchewan
- Construction start
- Jul 15, 2014(actual)
- Construction end
- Nov 30, 2014(actual)