Highway 39 - Northwest of Estevan
Federal contribution
$3.6M
$3,550,929
Federal share50%
of $7.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 13, 2013
20142015
Built
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Saskatchewan
- Construction start
- May 20, 2014(actual)
- Construction end
- Sep 30, 2015(actual)
Against the original forecast
- Construction start7 weeks lateforecast Mar 31, 2014
- Construction end10 months lateforecast Nov 30, 2014
Also in Estevan