Works to increase capacity of potable water reserves, upgrade to standards
Federal contribution
$4.5M
$4,512,256
Federal share25%
of $18.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201520162017
Built
Approved 23 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Régie Intermunicipale de l'Eau de la Vallée du Richelieu
- Construction start
- Sep 1, 2014(actual)
- Construction end
- Jun 23, 2017(actual)
Against the original forecast
- Construction end18 months lateforecast Dec 31, 2015