Highway 104: Paqtnkek Interchange
Federal contribution
$6.4M
$6,430,000
Federal share50%
of $12.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
20182019
Built
Approved 6 months before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Dec 22, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2017
- Construction end3 months earlyforecast Mar 31, 2019
Also in Antigonish
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44958 in the federal list. How to read these figures.