Upgrade to standards - water treatment plant

Acton Vale, Quebec

completeDrinking WaterCC
Federal contribution
$889,106
Federal share25%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2015201620172018
Built

Approved 22 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Acton Vale
Construction start
Nov 14, 2014(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Aug 4, 2014
  • Construction end3.4 years lateforecast Mar 30, 2015

Also in Acton Vale

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44986 in the federal list. How to read these figures.