Conversion of Temporary Community Flood Protection to Permanent
Federal contribution
$6.3M
$6,306,986
Federal share46%
of $13.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 18, 2014
20152016201720182019
Built
Approved 2 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Manitoba
- Construction start
- Sep 30, 2014(actual)
- Construction end
- Nov 30, 2018(actual)