Rehabilitation of Trans-Canada Highway in Newfoundland (Between Gambo and Benton)
Gambo, Newfoundland and Labrador
Federal contribution
$3.4M
$3,350,217
Federal share43%
of $7.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2014
20152016
Built
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Newfoundland and Labrador
- Construction start
- Nov 24, 2014(actual)
- Construction end
- Oct 3, 2016(actual)
Against the original forecast
- Construction start4 months lateforecast Jul 30, 2014
- Construction end4 weeks earlyforecast Oct 31, 2016
Also in Gambo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45082 in the federal list. How to read these figures.