Phase 1 of The Cartier Regional Water Cooperative Expansion

Headingley, Manitoba

completeDrinking WaterNRP
Federal contribution
$12.1M
$12,070,000
Federal share28%

of $43.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2014
201520162017201820192020
Built

Approved 4 weeks after the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jul 25, 2014(actual)
Construction end
Nov 28, 2019(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Aug 15, 2014
  • Construction end3 months lateforecast Sep 1, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45136 in the federal list. How to read these figures.