Phase 1 of The Cartier Regional Water Cooperative Expansion
Federal contribution
$12.1M
$12,070,000
Federal share28%
of $43.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2014
201520162017201820192020
Built
Approved 4 weeks after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Cartier Regional Water Cooperative Inc.
- Construction start
- Jul 25, 2014(actual)
- Construction end
- Nov 28, 2019(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Aug 15, 2014
- Construction end3 months lateforecast Sep 1, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45136 in the federal list. How to read these figures.