NHS - Route 11 Bypass & Twinning (Route 15 to Southside of Shediac River)
Federal contribution
$27.0M
$27,000,000
Federal share50%
of $54.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 26, 2014
ApprovedMar 27, 2015
20152016201720182019
Built
Approved 9 months after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Aug 3, 2015(actual)
- Construction end
- Jul 8, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast May 31, 2015
- Construction end8 months lateforecast Oct 31, 2018