PEI NHS Project - Tryon/Bonshaw/Marshfield
Federal contribution
$1.7M
$1,659,035
Federal share47%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2014
2015
Built
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Government of Prince Edward Island
- Construction start
- Aug 18, 2014(actual)
- Construction end
- Oct 31, 2015(actual)
Against the original forecast
- Construction end13 months lateforecast Sep 30, 2014