Aerotech Wastewater Treatment Facility (WWTF) Upgrade and Expansion
Federal contribution
$7.0M
$7,000,000
Federal share33%
of $21.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 15, 2014
ApprovedJun 16, 2015
2015201620172018
Built
Approved 6 months after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Halifax Regional Water Commission
- Construction start
- Sep 30, 2016(actual)
- Construction end
- Aug 24, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast May 2, 2016
- Construction end6 months lateforecast Feb 28, 2018