Aerotech Wastewater Treatment Facility (WWTF) Upgrade and Expansion

Halifax, Nova Scotia

completeWastewaterNRP
Federal contribution
$7.0M
$7,000,000
Federal share33%

of $21.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 15, 2014
ApprovedJun 16, 2015
2015201620172018
Built

Approved 6 months after the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Sep 30, 2016(actual)
Construction end
Aug 24, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast May 2, 2016
  • Construction end6 months lateforecast Feb 28, 2018

Also in Halifax