Northwest Territories Highway Capacity Improvements
Behchokö (Rae-Edzo), Northwest Territories
Federal contribution
$72.0M
$72,000,000
Federal share75%
of $96.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 27, 2015
201620172018201920202021
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Northwest Territories Ministry of Infrastructure
- Construction start
- Jun 11, 2015(actual)
- Construction end
- Mar 31, 2021(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jul 1, 2015
- Construction end2 years lateforecast Mar 31, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45786 in the federal list. How to read these figures.