Highway 7 Twinning: West of Saskatoon to Delisle
Federal contribution
$27.5M
$27,500,000
Federal share46%
of $59.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2015
201520162017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of Saskatchewan
- Construction start
- May 26, 2015(actual)
- Construction end
- Sep 15, 2020(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Jun 30, 2015
- Construction end4 months lateforecast May 31, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45826 in the federal list. How to read these figures.