Back to projects

Highway 77 - Fort Nelson River Bridge and Highway 97 - Passing Lane

Fort St. John, British Columbia

completeHighways and RoadsNRP
Federal contribution
$16.1M
$16,121,985
Federal share50%

of $32.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 24, 2015
20162017
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Nov 3, 2015(actual)
Construction end
Oct 3, 2017(actual)