Northwest Regional Airport Facility Expansion

Kitimat-Stikine, British Columbia

completeRegional And Local AirportsNRP
Federal contribution
$4.4M
$4,442,357
Federal share33%

of $13.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2015
201620172018
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Sep 27, 2015(actual)
Construction end
Jun 28, 2018(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 15, 2015
  • Construction end4 weeks lateforecast May 31, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45845 in the federal list. How to read these figures.