Yukon Resource Gateway

Carmacks, Yukon

underwayHighways and RoadsNIC
Federal contribution
$247.4M
$247,381,000
Federal share68%

of $362.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 2, 2017
ApprovedJul 24, 2019
today
20182021202420272030
BuiltForecast

Approved 23 months after the announcement.

Program
National Infrastructure Component
Construction start
Nov 3, 2021(actual)
Construction end
Oct 15, 2030(forecast)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45859 in the federal list. How to read these figures.