Highway 11/17 Coughlin Road Easterly to Red Rock Road 9 (including Black Sturgeon River Bridges) Expansion
Federal contribution
$26.1M
$26,050,000
Federal share42%
of $61.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 15, 2017
today
20172020202320262029
BuiltForecast
Approved 8 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Ontario Ministry of Transportation
- Construction start
- Jul 1, 2026(forecast)
- Construction end
- Aug 30, 2029(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45875 in the federal list. How to read these figures.