Highway 11/17 - 4 Lane Expansion: Highway 587 to Pearl Creek
Federal contribution
$30.0M
$30,000,000
Federal share42%
of $72.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 15, 2017
20172019202120232025
BuiltForecast
Approved 8 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Ontario Ministry of Transportation
- Construction start
- Mar 1, 2022(actual)
- Construction end
- Jun 1, 2026(forecast)
Against the original forecast
- Construction start15 months lateforecast Dec 2, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45876 in the federal list. How to read these figures.