Back to projects

Highway 404 - High Occupancy Vehicle Lanes

Markham, Ontario

completeHighways and RoadsNRP
Federal contribution
$46.1M
$46,057,500
Federal share50%

of $92.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 9, 2016
20172019202120232025
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jun 1, 2017(actual)
Construction end
Sep 28, 2024(actual)

Against the original forecast

  • Construction end10 months lateforecast Nov 30, 2023

Also in Markham