Back to projects

Renovation of municipal infrastructure - Garden City Avenue

Sainte-Anne-de-Bellevue, Quebec

completeDrinking WaterCC
Federal contribution
$286,465
Federal share33%

of $859.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2016
Built

Approved 9 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
May 28, 2015(actual)
Construction end
Aug 16, 2016(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2015
  • Construction end14 months lateforecast Jun 30, 2015

Also in Sainte-Anne-de-Bellevue