Replacement of water, sewer, and storm mains.
Federal contribution
$279,720
Federal share33%
of $839.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20162017
Built
Approved 9 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Prévost
- Construction start
- May 6, 2015(actual)
- Construction end
- Dec 12, 2016(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 1, 2015
- Construction end14 months lateforecast Oct 1, 2015
Also in Prévost
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45881 in the federal list. How to read these figures.