Replacement of water, sewer, and storm mains.

Prévost, Quebec

completeDrinking WaterCC
Federal contribution
$279,720
Federal share33%

of $839.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20162017
Built

Approved 9 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Prévost
Construction start
May 6, 2015(actual)
Construction end
Dec 12, 2016(actual)

Against the original forecast

  • Construction start3 months earlyforecast Aug 1, 2015
  • Construction end14 months lateforecast Oct 1, 2015