Replacement of water, sewer, and storm mains.
Federal contribution
$519,919
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20162017
Built
Approved 9 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of La Conception
- Construction start
- Feb 20, 2015(actual)
- Construction end
- Dec 31, 2016(actual)
Against the original forecast
- Construction start3 months earlyforecast May 15, 2015
- Construction end17 months lateforecast Jul 20, 2015
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45882 in the federal list. How to read these figures.