Back to projects

Inuvik to Tuktoyaktuk Highway

Inuvik, Northwest Territories

completeHighways and RoadsITH
Federal contribution
$200.0M
$200,000,000
Federal share72%

of $279.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 4, 2013
2013201520172019
Built

Approved 8 weeks before the announcement.

Program
Inuvik to Tuktoyaktuk Highway Program
Construction start
Dec 1, 2013(actual)
Construction end
Nov 15, 2018(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Dec 15, 2013
  • Construction end4 weeks lateforecast Oct 18, 2018

Also in Inuvik