Rehabilitation of water and sewer mains - Jean-Rioux and Notre-Dame East Streets
Federal contribution
$1.3M
$1,341,189
Federal share33%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2016201720182019
Built
Approved 9 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Trois-Pistoles
- Construction start
- Mar 21, 2016(actual)
- Construction end
- Dec 10, 2018(actual)
Against the original forecast
- Construction start6 weeks earlyforecast May 1, 2016
- Construction end8 weeks lateforecast Oct 12, 2018
Also in Trois-Pistoles
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45892 in the federal list. How to read these figures.