Back to projects

Rehabilitation of water and sewer mains - Jean-Rioux and Notre-Dame East Streets

Trois-Pistoles, Quebec

completeWastewaterCC
Federal contribution
$1.3M
$1,341,189
Federal share33%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2016201720182019
Built

Approved 9 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Trois-Pistoles
Construction start
Mar 21, 2016(actual)
Construction end
Dec 10, 2018(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast May 1, 2016
  • Construction end8 weeks lateforecast Oct 12, 2018

Also in Trois-Pistoles

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45892 in the federal list. How to read these figures.