Phase 2 - Arterial Roads Rehabilitation
Federal contribution
$800,000
Federal share33%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 16, 2015
20162017
Built
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Regional Municipality of Cape Breton
- Construction start
- May 2, 2016(actual)
- Construction end
- Oct 31, 2017(actual)
Against the original forecast
- Construction start2 months earlyforecast Jul 4, 2016
- Construction end5 months earlyforecast Mar 31, 2018
Also in Cape Breton
- Cape Breton Regional Municipality - Wastewater Treatment Infrastructure$39.2M
- Cape Breton University - Centre for Discovery and Innovation$20.0M
- Eskasoni First Nation Long Term Care Kiknu$19.7M
- Sydney Harbour West Wastewater Collection and Treatment$19.3M
- CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2$16.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45893 in the federal list. How to read these figures.