Replacement of water mains for Brasseur and Monseigneur Desmarais streets
Federal contribution
$469,192
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201520162017
Built
Approved 9 months before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Acton
- Construction start
- Dec 23, 2014(actual)
- Construction end
- Jul 12, 2017(actual)
Against the original forecast
- Construction start4 months earlyforecast May 1, 2015
- Construction end18 months lateforecast Dec 31, 2015
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45899 in the federal list. How to read these figures.