PEI Highway Rehabilitation Bundle
Borden-Carleton, Prince Edward Island
Federal contribution
$5.7M
$5,655,509
Federal share38%
of $15.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 14, 2015
2016
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Government of Prince Edward Island
- Construction start
- Jun 30, 2015(actual)
- Construction end
- Jul 14, 2016(actual)
Against the original forecast
- Construction end8 months lateforecast Oct 30, 2015
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45975 in the federal list. How to read these figures.