Water Transmission Main Renewal/Redundancy
Federal contribution
$5.1M
$5,066,666
Federal share33%
of $15.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 31, 2015
ApprovedJan 15, 2016
201620172018201920202021
Built
Approved 6 months after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Halifax Regional Water Commission
- Construction start
- Oct 20, 2016(actual)
- Construction end
- May 16, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Jul 4, 2016
- Construction end2 weeks earlyforecast May 31, 2021
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45987 in the federal list. How to read these figures.