Highway 85 - Phase 3

Saint-Antonin, Quebec

underwayHighways and RoadsNIC
Federal contribution
$389.7M
$389,661,618
Federal share45%

of $862.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 13, 2015
ApprovedJun 16, 2016
today
20162019202220252028
BuiltForecast

Approved 11 months after the announcement.

Program
National Infrastructure Component
Construction start
Sep 7, 2018(actual)
Construction end
Oct 31, 2027(forecast)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45989 in the federal list. How to read these figures.