Elton Waterline Expansion - Phase 1

Elton, Manitoba

completeDrinking WaterSCF
Federal contribution
$1.3M
$1,333,933
Federal share33%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 7, 2014
20152016
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 19, 2015(actual)
Construction end
Sep 28, 2016(actual)

Against the original forecast

  • Construction end5 weeks earlyforecast Oct 31, 2016