Treherne Waterline Renewal - Phase 1 & 2: Critical Areas
Federal contribution
$388,485
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 12, 2014
20152016
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Norfolk Treherne
- Construction start
- May 2, 2016(actual)
- Construction end
- Sep 15, 2016(actual)
Against the original forecast
- Construction start10 months lateforecast Jun 30, 2015
- Construction end5 months earlyforecast Jan 31, 2017