Ralls Island Rural Waterline Expansion

Kelsey, Manitoba

completeDrinking WaterSCF
Federal contribution
$979,810
Federal share33%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 24, 2014
201520162017
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Mar 4, 2016(actual)
Construction end
Apr 7, 2017(actual)

Against the original forecast

  • Construction end7 weeks lateforecast Feb 17, 2017