Improvements to the municipal water treatment plant
Eel River Crossing, New Brunswick
Federal contribution
$99,981
Federal share33%
of $299.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2015
2016201820202022
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Eel River Crossing
- Construction start
- Dec 17, 2015(actual)
- Construction end
- Nov 17, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast Nov 2, 2015
- Construction end12 months earlyforecast Nov 30, 2023
Also in Eel River Crossing
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46043 in the federal list. How to read these figures.