Back to projects

Replacement of pipes on Lebel street

Saint-François-de-Madawaska, New Brunswick

completeDisaster MitigationSCF
Federal contribution
$14,726
Federal share22%

of $68.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 8, 2015
2016
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 6, 2016(actual)
Construction end
Aug 31, 2016(actual)

Against the original forecast

  • Construction start11 months earlyforecast May 1, 2017
  • Construction end11 months earlyforecast Jul 28, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46065 in the federal list. How to read these figures.