Replacement of pipes on Lebel street
Saint-François-de-Madawaska, New Brunswick
Federal contribution
$14,726
Federal share22%
of $68.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 8, 2015
2016
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Saint-François-de-Madawaska
- Construction start
- Jun 6, 2016(actual)
- Construction end
- Aug 31, 2016(actual)
Against the original forecast
- Construction start11 months earlyforecast May 1, 2017
- Construction end11 months earlyforecast Jul 28, 2017
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46065 in the federal list. How to read these figures.