Sherridon Water Treatment Plant Upgrades

Sherridon, Manitoba

completeDrinking WaterSCF
Federal contribution
$466,666
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 24, 2014
2015201720192021
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Sherridon
Construction start
Apr 8, 2020(actual)
Construction end
Jun 7, 2021(actual)

Against the original forecast

  • Construction start4 months earlyforecast Aug 4, 2020
  • Construction end10 months earlyforecast Mar 31, 2022

Also in Sherridon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46129 in the federal list. How to read these figures.