Sherridon Water Treatment Plant Upgrades
Federal contribution
$466,666
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 24, 2014
2015201720192021
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Sherridon
- Construction start
- Apr 8, 2020(actual)
- Construction end
- Jun 7, 2021(actual)
Against the original forecast
- Construction start4 months earlyforecast Aug 4, 2020
- Construction end10 months earlyforecast Mar 31, 2022
Also in Sherridon