Construction of Water Reservoir and Transmission Line

Houston, British Columbia

completeDrinking WaterSCF
Federal contribution
$747,562
Federal share33%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
201620172018
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
District of Houston
Construction start
Jul 4, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction end2 months lateforecast Oct 31, 2017

Also in Houston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46146 in the federal list. How to read these figures.