Sewage Treatment Plant Retrofit
Federal contribution
$1.2M
$1,200,000
Federal share33%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 27, 2015
201620172018
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- District of Kitimat
- Construction start
- Jun 7, 2017(actual)
- Construction end
- Jun 13, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 8, 2017
- Construction end6 weeks earlyforecast Jul 27, 2018