Natural Hazard Risk Mitigation and Safety Improvements for Magnesia and Harvey Creek Water Intakes
Federal contribution
$97,550
Federal share27%
of $362.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 29, 2015
201620172018
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Lions Bay
- Construction start
- Dec 2, 2015(actual)
- Construction end
- Nov 30, 2017(actual)
Against the original forecast
- Construction start5 months lateforecast Jul 15, 2015
- Construction end14 months lateforecast Sep 30, 2016
Also in Lions Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46151 in the federal list. How to read these figures.