Bluewater Shoreline Small Diameter Watermain Replacement
Federal contribution
$97,690
Federal share33%
of $293.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 16, 2015
20162017
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Bluewater
- Construction start
- Nov 1, 2016(actual)
- Construction end
- May 18, 2017(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 18, 2016
- Construction end7 weeks lateforecast Mar 31, 2017
Also in Bluewater
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46178 in the federal list. How to read these figures.