Grandview Drive & Susan Street Reconstruction / Development of Alternate Water Distribution Trunk Main
Federal contribution
$909,500
Federal share33%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2015
20162017
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Meaford
- Construction start
- Apr 18, 2016(actual)
- Construction end
- Sep 18, 2017(actual)
Against the original forecast
- Construction start2 weeks lateforecast Apr 1, 2016
- Construction end11 months lateforecast Oct 31, 2016
Also in Meaford