Main Street Reconstruction

Penetanguishene, Ontario

completeWastewaterSCF
Federal contribution
$1.7M
$1,746,666
Federal share33%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 22, 2015
2016201720182019
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Penetanguishene
Construction start
Apr 3, 2018(actual)
Construction end
May 9, 2019(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Apr 18, 2018
  • Construction end4 months lateforecast Dec 31, 2018

Also in Penetanguishene

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46193 in the federal list. How to read these figures.