Schedule
Announced and approvedJul 22, 2015
2016201720182019
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Penetanguishene
- Construction start
- Apr 3, 2018(actual)
- Construction end
- May 9, 2019(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Apr 18, 2018
- Construction end4 months lateforecast Dec 31, 2018