Old Barrie Road East and Highway 11 South Ramp and Northbound Ramp Intersection Improvements
Federal contribution
$741,000
Federal share30%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 22, 2015
20162017
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Orillia
- Construction start
- Jun 9, 2016(actual)
- Construction end
- Sep 1, 2017(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 16, 2016
- Construction end5 months lateforecast Mar 31, 2017
Also in Orillia
- Design and construct a new transit terminal$4.0M
- Construction of a Public Library and Market Square$1.9M
- Replace Conventional and Specialized Buses$1.8M
- Improvements to the Coldwater Water Distribution System$1.5M
- Upgrade the Wastewater Treatment Centre and Construct Tertiary Filter and Blower Buildings for Process Optimization, and Tertiary Treatment to meet Lake Simcoe Effluent phosphorus limits$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46215 in the federal list. How to read these figures.