Plaunt Street South Rehabilitation

Renfrew, Ontario

completeDrinking WaterSCF
Federal contribution
$633,685
Federal share33%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2015
2016
Built

Approved 5 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Renfrew
Construction start
May 17, 2016(actual)
Construction end
Nov 4, 2016(actual)

Against the original forecast

  • Construction start3 months lateforecast Mar 1, 2016
  • Construction end8 weeks earlyforecast Dec 30, 2016