Water and Sewer Rehabilitation and related works - King Street, Havelock, Ontario
Havelock-Belmont-Methuen, Ontario
Federal contribution
$679,078
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 21, 2015
201620172018
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Township of Havelock-Belmont-Methuen
- Construction start
- Nov 2, 2015(actual)
- Construction end
- Dec 31, 2017(actual)
Against the original forecast
- Construction start8 months earlyforecast Jul 4, 2016
- Construction end4 months lateforecast Aug 25, 2017
Also in Havelock-Belmont-Methuen
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46228 in the federal list. How to read these figures.