Route 389 Improvement between Baie-Comeau and Fermont
Federal contribution
$183.0M
$183,000,360
Federal share48%
of $384.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 27, 2018
today
2018202120242027
BuiltForecast
Approved 7 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Quebec Ministry of Transport
- Construction start
- Apr 3, 2019(actual)
- Construction end
- Sep 30, 2028(forecast)
Against the original forecast
- Construction start14 months lateforecast Jan 31, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46250 in the federal list. How to read these figures.