Town of Nanton Wastewater Treatment Plant

Nanton, Alberta

completeWastewaterSCF
Federal contribution
$1.8M
$1,750,000
Federal share15%

of $12.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Nanton
Construction start
Apr 18, 2016(actual)
Construction end
Oct 30, 2017(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 1, 2016