County of Wetaskiwin Alder Flats Wastewater Expansion

Wetaskiwin No. 10 (County), Alberta

completeWastewaterSCF
Federal contribution
$981,867
Federal share33%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
20162017201820192020
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Wetaskiwin No. 10 County
Construction start
Jan 1, 2016(actual)
Construction end
Sep 30, 2020(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Oct 31, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46260 in the federal list. How to read these figures.