Village of Empress Water Distribution Pump Station Replacement
Federal contribution
$416,666
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
201620172018201920202021
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Empress
- Construction start
- Feb 9, 2019(actual)
- Construction end
- Feb 12, 2021(actual)
Against the original forecast
- Construction start13 months lateforecast Jan 1, 2018
- Construction end7 months lateforecast Jun 30, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46263 in the federal list. How to read these figures.